- BLS broke the pull rope while trying to pull main electrical feeders to the Dewatering Building. They also tore the insulation on one of the feeders while pulling the wire back out. They have a replacement wire and will try to pull again on Monday.
- Trying to pressure test 4" PLW line at Lime Silo re-route but can't get the line to hold pressure. Either we have a leak in the line or WS has valves open inside the building (we told them to close everything). Will have to start searching for the leak on Monday.