bmeadows100

St Pete Biosolids
2018-01-08 00:00:00 (UTC)

Monday

- Hallsten setting bridges for Clarifier #2 lid.
- Shoring for Batch Tank lid did not arrive today. Should be on site tomorrow.
- Layout for Sludge Pump pad is off. Our concrete is 8" out of square due to a mistake in the modeling from our BIM department.