Wednesday

- Bob Bruner on site.
- Confirmed correct details of Clarifier Stair piers thru approved rebar shop drawings. We did order the wrong size sono-tubes. Also, running into issues with ground water. Past 6-ft deep (8'6" required), the ground water and sugar sand caves in the excavation. Tried to get deep enough and pour a mud mat but did not work. Joe Kantor to speak to the engineer.
- Joe Kantor (and PM staff) back on site. Discussed priority issues with Joe this AM, mainly Leak Test of Clarifier, standard of finish on tanks, and materials for DW Bldg Electric Room.
- Eagle Steel asked for confirmation from the rebar manufacturer (Gredau) that the shop drawings, showing radius bar on bottom of mat, are correct. Eagle said that is not the way rebar is typically installed. Aaron Kanouse (APM) called Gredau and they confirmed.