bmeadows100

St Pete Biosolids
2018-01-15 00:00:00 (UTC)

Monday

- Oni did not order the right mix design for the HVAC pad at the Dewatering Bldg. He failed to specifically ask for the Vaporlock ad-mixture. Concrete company is trying to locate because they did not have it on hand. Will not pour today.
- Sawcutters to be on site tomorrow for the re-work at the Generator. No one has coordinated the layout yet. Randy and I had to lay out the proposed cuts, BL Smith will review tomorrow morning before we start cutting. I do not know why Ring Power is not on site overseeing this since it was their mistake.