St Pete Biosolids
2018-01-11 00:00:00 (UTC)

Thursday

- Spoke to Tim Hume about dividing the cost of removing the concrete pile among Biosolids and ICI. Tim was good with Biosolids incurring 2/3 and ICI with 1/3. I asked if he needed to run it by Mike Ryle and he said Mike would back it as long as he and Keith were ok.
- Will have to relocate installed PW and PLW lines around Lime Silo pad because this wasn't addressed early on. City is supposed to cover the cost.
- Met with Sherwin Williams rep about the epoxy coating and the cracks in the Dewatering Building slab. Sherwin Williams said the epoxy that was spec's would not cover the cracks in the concrete and he can can recommend a product but it will be more expensive. Supposed to get us some info.