- Met again with Wharton Smith and BL Smith about pipe at Sludge Pump Station. Wharton Smith suggested a different pipe layout than what was discussed yesterday. I instructed them to have their CADD department draw it up for us to review.
- Started filling Splitter Box for leak test.
- Crack Injection machine is still down. Ben ordered a new one but it won't be on site until Friday. Will have lost this entire week on Clarifier #1.
- Finally have a layout for the relocation of the Lime Silo system to the new Dewatering Building. This was not taken into account by the engineers and was not planned for so we had to figure everything out ourselves.